SeaSk8 Upd8 – Schedule

In a meeting yesterday, the city presented a rough schedule for the SeaSk8 replacement process. Dates can certainly change and our experience has been that things take longer not shorter, but since this will be the 5th SeaSk8 you would think that the parties involved should be getting better at this. Time will tell. Here is the rough schedule that was presented yesterday. Take note that currently the last weekend for a SeaSk8 session will be on October 6-7th. Details on a final blowout event will be posted here in the future.

Planning – (from now until the end of 2018)

  • Site determination and budget proposal: now until October 1
  • Closure of existing SeaSk8: October 8th, 2018
  • City Council budget approval process: 4th quarter of 2018

Design – (October 2018 – October 2019)

  • Design selection to contract signed: October 1st – December 31st
  • Public meetings and design process: 1st quarter of 2019
  • Design review and finalize: 2nd quarter 0f 2019
  • Permitting: 3rd quarter of 2019
  • Award bid: October 1st, 2019

Construction – (November 2019 – May 2020)

Park opens – Summer 2020

 